Saturday, March 31, 2007

Working On The Basics

Friday (3/30) was a busy day. Johnny and Chris of Eurocraft Hardwood Flooring started early (6:30am) sanding the entire first floor with "first paper" (36 grit). It's hard work because the sanding maching wants to "take off" and must be restrained fore and aft. (The "snowflakes" are the dust particles reflecting my flash light). This is what I've been waiting for... the seamless expanse from the front door into the kitchen. The white oak is gorgeous and the scent is to be remembered.
The weaving of the new and old wood is top notch!
The comes the filler ... to be sanded off with the next paper (50 grit).
By the end of the day the filler had dried.
Meanwhile, Dan and Greg near completion of the porch and its roof.

Quality work ...
Also, the Star Roofing crew completed installing the new roof. More pictures to follow ...

Wednesday, March 28, 2007

The Porch Continues ...

The porch is nearing completion. Roof trim, porch deck, railing and steps to come ...

"Pumpkin Cannon"

Nah, not really. This is the chimney from the wood-fired stove that used to be in the kitchen. Craig's list get ready ...

Let The Roofing Begin ...

Star Roofing arrived today, tearing off the old roof. The new roof will be installed tomorrow.

Monday, March 26, 2007

Raising The Roof

Today the guys from BRC (Dan and Glen) dug into the creation of the new porch roof. Old composite shingles were scraped off and preps made for the rafters. Duke prepares the miter on the header ...
Header in place ...
Rafters attached near the ridge line of the house, resting on the header...
The final form takes shape ...

Thursday, March 22, 2007

Front Porch Rising

Getting ready to secure the first post. The posts are pressure treated, suitable for direct contact with the ground. They are secured to the concrete pads with galvanized post brackets. Attaching the perimeter.
Floor joists ...
End of day...
Lookin' good...

Wednesday, March 21, 2007

The 4th Bedroom

Yesderday I worked on the fourth bedroom. It's in the basement. It measures 12.8 ft. by 9.6 ft and has a 6 ft. wide window looking out into the backyard. It will have a very large closet, and ample room for bed and furniture.

Job Well Done

That's Dan changing the power lines from the old mast to the new. The power lines came from the pole on the street (to the right) through some trees. A tree limb placed quite a load on the lines so Dan and Greg added "tree trimming" to their resumes.
Here's a shot of the finished product - the single, new mast with power connected.

And the new panel has been installed and energized.

Monday, March 19, 2007

Out With The Old & In With The New

Dan and Greg (Big Red Construction) spent the day pulling wire, creating outlets, switches and smoke detector boxes. By "quitting time" the new service panel was wired, ready for change over, save a few circuits remaining in the old box.

Progress In The Full Bath

Hand rail backing was installed first. It's horizontal center line is 28" above the tub side. A plastic vapor barrier was added next. Then came the 1/2" cement board in all areas in contact with the tub.
Seams have been covered with mesh tape and are ready for sealing.

Kitchen Floor Is In

Christian and Johnny (Eurocraft Hardwood Floors) finished laying the kitchen floor today. It looks great. Now it will sit for a few days as the wood and joints relax and tighten.
The first coarse sanding of the entire house will begin next week.
We'll sample stains and make a choice of floor color.

Saturday, March 17, 2007

Busy Day: Electical Upgrades

Here's a shot of the new electrical service panel. The existing service is 125 amp into a "split panel" box (no longer code). When this upgrade project is complete the house will have 200 amp service, a brand new panel, and ... A new meter box, and ...
A new mast, (that's Duke and Dan in action), and

And a new power connection from the pole at the street.



Busy Day: Porch Pads

It's early Friday morning. Duke and Greg are building forms for the concrete pads that will support the porch posts. Delivering the concrete ... Setting the rebar ...
The finished product, curing over the weekend, ready to begin porch construction next week.

Busy Day: Kitchen Flooring

We started the kitchen flooring this past week. It is exciting to see the progress. Here are Johnny and Christian of Eurocraft Hardwood Floors preparing to glue and nail the first row of white oak flooring. Johnny takes pride in his work. Here he is taking great care to weave the new wood with the old. Once the finishing work is complete, you won't be able to tell where the old stopped and the new begins.
Here's a bug's eye view of Christian working near the laundry area.
By the end of the day approximately 60% of the wood was down. Check out the view into the livingroom. Now imagine the view of the finished floor upon entry into the house!
More to report next week ...

Tuesday, March 13, 2007

If You Can't Stand The Heat ...

Today I worked on returning heat to the kitchen. I removed it last month during the demolition. Here is a shot of the duct as it comes out and down from the top of the basement furnace. It runs a few feet north, then up and east...
under the floor (I may reroute the wires above the vent) to its outlet near ...
the kitchen door. Its heat will enter the room from underneath a cabinet (blue outline) and be circulated by the ceiling fan.

Sunday, March 11, 2007

"Nothin' Like A Bigger Hammer"

It took me some time last week to move the dirt and rubble away from the concrete porch in preparation for Duke Davis (Big Red Construction aka BRC) to demolish the porch. Here's Duke with his hammer. Greg Gordon (BRC partner) is looking on ... and thinking "We need a bigger hammer." I'm thinking "I'm glad Duke talked me out of doing the job myself ("smaller hammer").
So, Dan Berlin (BRC partner) called in Bruce Baker, Excavator Extraordinaire, aka "The Bigger Hammer".
Even so, it was a challenge ... (That's Dan looking on.)
Until the porch deck gave way...
The rest of the job was reduced to rubble and dust...
Once the porch was in pieces, Bruce changed implments and began throwing chunks into his truck...
Part of the sidewalk...
Now the site is ready for Duke to begin construction of the new porch and roof.